Visited BH this afternoon and can confirm work is progressing fine.
Fuel tanks have been removed.
Work continues on the body framework, this is done section by section
to ensure the correct profile is maintained.
Pre-formed steelwork for both the outer and inner body skins has now all
been delivered and installation of the lower sections of the inner skin
has started.
Cab doors have been renovated and are now primed ready for refitting in
due course.
Engine room pipework sections previously removed has been renovated and
some sections will be replaced as they were badly corroded. Other sections
of pipework relating to obsolete equipment have been removed permanently.
Equipment is now on site to allow the defective generator to be split
from its engine for repair.
Basically everything is sound, there are lots of jobs that have been done
to remove parts from the main structure prior to renovation all of which
are time consuming but nevertheless important jobs.
|